Hi all,
BICEP2 team meeting today (Tues) will be 2-3pm Pacific, so that Walt can
join:
Phone: 1-866-890-3820 (toll: 1-334-323-7229) Passcode:59702175
group discussion terminates at 1 hour,
any wrap-up discussion < 90 min.
Here is today's agenda:
1) Weekly report from Pole [ Steff ]
- cryo
- bicep.rc / data transfer
- weather: cold and clear
2) Data quality / reduc czar report
This week's report [ Angiola's email ]
status of B2 2012 re-reduction [ Angiola/Randol ]
status of cut definitions / reduc to-do
Next week's czar?
3) General news and plans
- new mailing list working?
- SPIE papers posted...thanks.
4) Analysis pipeline news and plans
see notes below
- pipeline telecon Friday 10 Aug, 4 eastern, 3 central, 1 pacific
5) Other Postings
2012 Aug 1: Generating Synfast Maps with WMAP noise (JET) Updated Aug 3
2012 Aug 6: Sim 1205/1206 (CDS)
2012 Aug 6: Guide to running a simset (CDS)
end of today's agenda.
Notes from yesterday:
-----------------------------------------------------------------------
6 Aug 2012 B2 analysis/pipeline telecon
On the line: John, Randol, Colin, Abby, Chris, Angiola, Jon
B2 reduction (2:00-2:30 eastern) -----------------
status of Angiola's B2 2012 re-reduction
[ Angiola / Randol / Chris to summarize ]
disk space on bicepfs1 and panlfs
- John to ask P Edmon again for quotes [done, quotes for 56 TB more
are coming]
status of thermal stability from Jon:
- Jon is working on season-split (alternate days?) NTD jacks
- will post updated outline of thermal stability project/paper for
tomorrow
Pipeline telecon (2:30-3:30 eastern) ----------------------
WMAP-like noise added to synfast input maps
- Jamie Tolan not on, but briefly discussed his posting (further
discussion Tue/Fri)
- IDL-free, incl. matlab fits binary writer -- awesome.
- noise levels (e.g. 67uK) defined for what area?
- Should we consider more than W-band? Randol says yes, V-band is
what he used.
Abscal: Chris recently changed get_ukpervolt for B2 to 3071, from 3605.
- We need clear abscals for each different B2 epoch!
- Angiola to ask Justus for summary of work done on this, incl. vs.
ell consistency
Plan for closed loop sim/deproj tests:
1. input sim systematics @ best guess B2 level. What are these?
a. relgain--we need closure from per-det abscal or per-pair T/dif
leakage [ Justus / Walt?]
http://bmode.caltech.edu/~spuder/analysis_logbook/analysis/20120117_wmapxco…
b. diff pointing - beams_ab_cmb_bicep2_20100101.csv (per det fits
from CMB, Walt)
c. diff beam size - ?
d. diff ellipticity - ?
2. generate timestreams using 3 sim algorithms:
a1. linear systematic introduced using same template as deproj
a2. best realistic model
a3. best realistic model x2
a1 gives us a check to numerical accuracy (for deprojection on nopol
input) and a clean test of E-to-B only (for deprojection on EnoB input).
a2 or a3 is what we use by default; the ability to increase accuracy
by 2x (e.g. doubling nsides, or the number of beamwidths used for
interpolation) and verify negligible difference in coadded output maps
assures us that sim timestreams are “close enough to reality”.
3. Deproj using linear basis constructed from derivatives.
what is status of gen_templates? [Randol]
width/ellipticity? strategy for interpolation?
Randol's posting here serves as a model:
http://bicep.caltech.edu/~spuder/analysis_logbook/analysis/20120404_diffpoi…
We need to identify a limited set of tags to run this on, and run full
signal (nopol, EnoB, BnoE) and scaled-noise sims.
Each of the signal sims should be generated without systematics, and
with systematics using the 3 sim algorithms.
Each of these simsets should be mapped and processed to aps with and
without deprojection.
We do this first for relgain, diffpoint, and diffwidth separately, and
then in combinations.
Hi All,
Observing:
----------
120923 07:38:24 - still running
* 9_CMB_36d_dk248_015.sch
120923 07:29:12 - 120923 07:30:37
* mce_autotune.sch
* MASD restart, DSP driver reload & mce_reset_clean, GCP restart
after running schedule.
120923 07:25:11 - 120923 07:25:28
* mce_autotune.sch
* Failed
120923 02:00:05 - 120923 02:05:43
* do_cycle.sch
* Tilts:
az 0° 180°
x -8.904 -9.432
y 9.602 10.514
* dk=0 mark OK
* cleaned GS, boot, UFB, LFB, window
* Membrane 0.12/0.40
120920 07:36:26 - 120923 01:39:14
* 9_CMB_36d_dk113_015.sch
120920 07:28:46 - 120920 07:30:11
* mce_autotune.sch
* MASD restart, DSP driver reload & mce_reset_clean, GCP restart
after running schedule.
120920 02:14:44 - 120920 02:20:29
* do_cycle.sch
* Tilts:
az 0° 180°
x -8.904 -9.377
y 9.393 10.778
dk=0 mark OK
cleaned GS, boot, UFB, LFB, window
Membrane 0.12/0.4
120917 07:52:21 - 120920 01:51:02
* 9_CMB_36d_dk068_015.sch
* MCE error @ 120917 15:20:57:
/usr/mce/mce_script//script/mce_update_userword: line 27:
array_integer + 256 * Reply does not match command. : syntax error:
invalid arithmetic operator (error token is ". ")
* MCE error @ 120918 16:04:58:
/home/bicep/gcp/control/../masd/specific/scripts/mce_fast_pipe:
line 74: 50000000 / Reply does not match command. / 60 : syntax error:
invalid arithmetic operator (error token is ". / 60 ")
/home/bicep/gcp/control/../masd/specific/scripts/mce_fast_pipe:
line 77: / 140 : syntax error: operand expected (error token is "/ 140 ")
Telescope:
----------
- A few non-fatal MCE errors
- Load leveler room exhaust fan troubles continue. The fan belt broke on
the cooling air handler. Managed to get it under control before we
started scanning on 9/20. Cynthia saved the day. She was the only one
small enough to be able to reach the belt (marvel of engineering).
Even before this happened, I requested the motor to be changed, as it
was quite noisy. This will happen tomorrow during the fridge cycle.
Right now it is getting too cold in the load leveler room. Waiting for
someone to turn up to look at it.
Weather
--------
- Windy and overcast, followed by some clear days
Cryogenics:
-----------
* Tracking spreadsheet at
http://bicep.rc.fas.harvard.edu/bicep2/south_pole_helium_usage/Summer_2011_…
Boiling off remaining liquid in Simon and pumping it into the half rack.
* Kathleen's Cryo Sitrep:
LHe:
• Approximately 4400 liters of useable LHe remain in the Wessington dewars.
• Approximately 250 liters of LHe were delivered to BICEP2.
• Based on a historical consumption rate of 35.7 liters/day, LHe
supplies are expected to be exhausted by January 2013
GHe:
• Out of 16 storage tanks for gaseous helium: 7 tanks are at 17.2 MPa
(2500 psi), one tank is at 13.8 MPa (2000 psi), one tank is at 10.3 MPa
(1500 psi), one tanks is at 5.7 MPa (850 psi), one tank is at 3.5 MPa
(500 psi), one tank is at 1.4 MPa (200 psi), two tanks are at 1.0 MPa
(150 psi), and two tanks are at 0 MPa (0 psi).
• Vent GHe from the LHe transfer was compressed into the storage tanks.
LN2:
• The liquid nitrogen plant tuned off all week
• Approximately 300 liters of LN2 are currently stockpiled on station.
Analysis/software/computers:
----------------------------
- Nothing to report
Cheers,
Steffen
11 Sep 2012 BICEP2 weekly telecon
On the line:
Havard: John Kovac
Stanford: Walt, Jamie T.
JPL: Hien
Caltech: Randol, Jamie B., Pete, Jeff
San Diego: Jon Kaufman
Minnesota: Clem, Stefan, Chris
1) Weekly report from Pole [ Steff ]
- looks like another good CMB week, weather good to overcast
- load leveler fan / bldg temp disruptions during last schedule
Do we have a way to pinpoint this?
- cryo: drawing down Theo now, looking fine
2) Data quality / reduc czar report
Aug 18 - Sep 1 report [ Randol ]
Missing reducplots
Need fixes to code checking all reducplots made
Listed large # tags missing round 1 / round 2 cut
plots AI: Randol to fix code
AI: Look at why jobs are failing -- timing out
short_serial? Stationarity_ab cut removing large amount of data.
Some scansets with mediocre weather not being removed by
elnod cuts. 20120827C07 -- looks like v. large sky gradient,
bleeding into pair diff p1-3 modes. Not cut!
should it be? Does the p3 filtered data look OK?
20120830B01 -- snow on window? Correctly cut.
But passing most elnod cuts!
This week's report (email?) [Jon]
Recently generated tag browser
Mostly looks OK...
AI: Jon to study reducplots, present next week
next week's czar
status of B2 mass re-reduction [ Angiola/Randol ]
AIFL: stationarity_ab cut: Angiola/Jamie
AI: Walt to check in el nod gap cut
AIFL: elnod goodness-of-fit cut: Martin, status? -- remains open
outstanding B2 mass reduction actions?
3) Deployment/operations planning:
http://bicep.caltech.edu/~spuder/schedule/A-039_FY13_deployment.html
updated list emailed around
Steff would like to leave around Nov. 20
- November/December measurement plan [ Randol / Colin ]
- report on final B2 calibrations
most moon and BNS source data are not ideal for beam parameters
because of size of signal. need target ADU strength for ideal
beam shape meas.
- Zak to prepare FTS for Keck, also use for BICEP2
- October testing: thermal studies [ Jon ]
- To retro:
BICEP2 cryostat
other items? talk to John
items with JPL stickers that must go back to JPL
AI: Randol to look into these
4) Analysis updates:
- thermal analysis update? [ Jon ]
- UCSD proposes to look at cosmic birefringence w/ B1 and B2 data
Threads to initial B2 result:
- baseline data reduction
- are we satisfied with deglitching / other low-level
reduc? Believe so; Clem has asked for additional studies to verify
- are cuts doing a sensible job eliminating poorly modeled
data? Few outstanding action items; see reduc czar section
- deprojection
- baseline: relgain + diffpoint deproj (per phase or longer)
- using WMAP7 T derived templates
- Kendrick derived B spectrum estimators
2012 Sep 10: Rel-gain regression in the presence of template noise (for
BICEP1) (RWA)
2012 Sep 10: Deprojection sims 1211-1220 (CDS)
- systematic characterization
- statistics for reporting limits, r constraints
- foregrounds
- hope that BICEP1 3-yr results can provide us a model
to follow for these points
- other B2 analysis threads
-------end B2 Team business----------------------
Hi All,
Observing:
----------
120917 07:52:21 - still running
* 9_CMB_36d_dk068_015.sch
* MCE error @ 120917 15:20:57:
/usr/mce/mce_script//script/mce_update_userword: line 27:
array_integer + 256 * Reply does not match command. : syntax error:
invalid arithmetic operator (error token is ". ")
120917 07:43:45 - 120917 07:45:10
* mce_autotune.sch
* MASD restart, DSP driver reload & mce_reset_clean, GCP restart
after running schedule.
120917 02:46:53 - 120917 04:14:50
* starpoint_pole_bicep_summer.sch
* Tilts: 10.492
az 0° 180°
x -8.904 -9.432
y 9.371
120917 02:24:19 - 120917 02:29:55
* do_cycle.sch
* dk=0 mark OK
* cleaned GS, boot, UFB, LFB, window
* Membrane 0.1/0.4
120914 08:14:11 - 120917 02:02:51
* 9_CMB_36c_dk293_015.sch
120914 08:07:53 - 120914 08:09:17
* mce_autotune.sch
* MASD restart, DSP driver reload & mce_reset_clean, GCP restart
after running schedule.
120914 08:05:10 - 120914 08:05:54
* mce_autotune.sch
* Failed
120914 02:37:50 - 120914 02:43:27
* do_cycle.sch
* Tilts:
az 0° 180°
x -8.904 -9.432
y 9.371 10.492
dk=0 mark OK
cleaned GS, boot, UFB, LFB, window
Membrane 0.12/0.45
120911 08:18:49 - 120914 02:14:39
* 9_CMB_36c_dk248_015.sch
Telescope:
----------
- One pointing schedule
- One non-fatal MCE errors
- Load leveler temperature spiked and exhaust fan came on during 9/14
schedule. We worked for several hours throughout the night to
reconfigure things to lower the temperature. Still working on a
permanent fix. Weather was pretty bad during all this.
Weather
--------
- Windy and overcast, followed by some clear days
Cryogenics:
-----------
* Tracking spreadsheet at
http://bicep.rc.fas.harvard.edu/bicep2/south_pole_helium_usage/Summer_2011_…
* Kathleen's Cryo Sitrep:
LHe:
• Approximately 4600 liters of useable LHe remain in the Wessington dewars.
• Approximately 500 liters of LHe were delivered to BICEP2.
• Based on a historical consumption rate of 35.7 liters/day, LHe
supplies are expected to be exhausted by January 2013
GHe:
• Out of 16 storage tanks for gaseous helium: 7 tanks are at 17.2 MPa
(2500 psi), one tank is at 13.8 MPa (2000 psi), one tank is at 10.3 MPa
(1500 psi), one tanks is at 4.8 MPa (700 psi), three tanks are at 1.4
MPa (200 psi), two tanks are at 1.0 MPa (150 psi), and one tank is at 0
MPa (0 psi).
• Vent GHe from the LHe transfer was compressed into the storage tanks.
LN2:
• The liquid nitrogen plant tuned off all week
• Approximately 350 liters of LN2 are currently stockpiled on station.
Analysis/software/computers:
----------------------------
- Nothing to report
Cheers,
Steffen
All;
Superb pictures taken by Steffan in recent days.
Pete
-------- Original Message --------
Subject: Re: Sequence of Pictures of Sunrise.
Date: Tue, 11 Sep 2012 22:38:30 +1200
From: Steffen Richter (BICEP2) <Steffen.Richter.Guest(a)usap.gov>
To: Peter Mason <pmason(a)alumni.caltech.edu>
Pete,
Here are some recent pix.
Cheers,
Steffen
On 2012-09-10 15:22, Peter Mason wrote:
> Robert and Steffen;
>
> I wish I could be at the Pole for the next few days to watch
> the sun slowly peek above the horizon. I have seen pictures taken at
> the time that were gorgeous.
>
> Would either of you be interested in documenting it? I (and
> many others, I'm sure) would be greatly pleased to see a sequence of
> pictures, one a day at the same time and looking in the same
> direction, so we could make a sequence out of it.
>
> Of course, we'd also like pictures of all the other activity
> going on.
>
> Best
>
> Peter Mason
>
> Dr. Peter V. Mason
> MS 59-33
> California Institute of Technology
> 1201 E. California Bl.
> Pasadena, CA 91125
> Ph. 626-395-3341
> Fax 626-584-9929
> Email pmason(a)alumni.caltech.edu
Hi All,
Observing:
----------
120911 08:18:49 - still running
* 9_CMB_36c_dk248_015.sch
120911 08:09:28 - 120911 08:10:52
* mce_autotune.sch
* MASD restart, DSP driver reload & mce_reset_clean, GCP restart
after running schedule.
120911 02:47:26 - 120911 02:53:04
* do_cycle.sch
* Tilts:
az 0° 180°
x -8.904 -9.388
y 9.827 10.305
* dk=0 mark OK
* cleaned GS, boot, UFB, LFB
* Membran 0.12/0.45
120908 08:27:20 - 120911 02:26:25
* 9_CMB_36c_dk113_015.sch
* MCE error @ 20120910 15:48:28:
/home/bicep/gcp/control/../masd/specific/scripts/mce_fast_pipe:
line 74: 50000000 / Reply does not match command. / 60 : syntax error:
invalid arithmetic operator (error token is ". / 60 ")
/home/bicep/gcp/control/../masd/specific/scripts/mce_fast_pipe:
line 77: / 140 : syntax error: operand expected (error token is "/ 140 ")
120908 08:18:21 - 120908 08:19:46
* mce_autotune.sch
* MASD restart, DSP driver reload & mce_reset_clean, GCP restart
after running schedule.
120908 03:27:42 - 120908 07:17:58
* starpoint_pole_bicep_winter.sch
* Tilts:
az 0° 180°
x -8.674 -9.728
y 9.602 10.767
120908 03:00:41 - 120908 03:06:18
* do_cycle.sch
* dk=0 mark OK
* cleaned GS, boot, UFB
* Membran 0.10/0.40
120905 08:35:47 - 120908 02:38:13
* 9_CMB_36c_dk068_015.sch
120905 08:31:57 - 120905 08:33:22
* mce_autotune.sch
* MASD restart, DSP driver reload & mce_reset_clean, GCP restart
after running schedule.
120905 03:04:31 - 120905 03:10:08
* do_cycle.sch
* Tilts:
az 0° 180°
x -8.904 -9.377
y 9.822 10.305
* dk=0 mark OK
* cleaned GS, boot, UFB
* Membran 0.12/0.43
120902 09:18:34 - 120905 02:50:02
* 9_CMB_36b_dk293_015.sch
Telescope:
----------
- One pointing schedule
- One non-fatal MCE errors
- Load leveler fan came on 3 times during the last schedule. We had a
cold spell of <-100F. When that happens, they need to switch to the
electric boiler, because the fuel gets to viscous for the pumps to work.
The electric boiler does not seem to be very well regulated. When it
warms up and we don't switch back to the furnace asap, it will get too hot.
Folks here are generally are not really on top of things. I had to raise
an alarm for the low temperature when we hit <-100F and again when
things got too warm. Good thing I installed all these sensors and tied
them into our radio pager :-)
We'll go through the same scenario again in the next few days. Let's see
if they do any better this time
Weather
--------
- Few days of cold and clear wx, followed by a warmer period with
overcast skies.
Cryogenics:
-----------
* Tracking spreadsheet at
http://bicep.rc.fas.harvard.edu/bicep2/south_pole_helium_usage/Summer_2011_…
* Kathleen's Cryo Sitrep:
LHe:
• Approximately 5000 liters of useable LHe remain in the Wessington dewars.
• Approximately 250 liters of LHe were delivered to BICEP2.
• Based on a historical consumption rate of 35.7 liters/day, LHe
supplies are expected to be exhausted by January 2013
GHe:
• Out of 16 storage tanks for gaseous helium: 6 tanks are at 17.2 MPa
(2500 psi), two tanks are at 13.8 MPa (2000 psi), one tank is at 10.3
MPa (1500 psi), one tanks is at 5.5 MPa (800 psi), one tank is at 2.0
MPa (300psi), two tanks are at 1.4 MPa (200 psi), two tanks are at 1.0
MPa (150 psi), and one tank is at 0 MPa (0 psi).
• Vent GHe from the LHe transfer was compressed into the storage tanks.
LN2:
• The liquid nitrogen plant tuned on 2 September 2012 and turner off 4
September 2012
• Approximately 400 liters of LN2 are currently stockpiled on station.
Analysis/software/computers:
----------------------------
- Nothing to report
Cheers,
Steffen